Project Description
The Southside Gateway will widen Woodville Highway from Capital Circle Southwest to Tram Road, which will enhance capacity along a key evacuation route.
Project Status
Blueprint has executed an agreement with FDOT for curb extensions and landscaping along the St. Marks Trail.
The FY 2023-2028 FDOT Work Program identifies the following funding in the project area:
- $415,100 for preliminary engineering and right-of-way funding for Woodville Highway improvements from Capital Circle to Gaile Ave.
- $2,167,661 for preliminary engineering and right-of-way funding for Woodville Highway from Gaile Ave. to Paul Russell Rd.
- $252,004 for construction of lighting along Crawfordville Rd from Capital Circle SW to Mckenzie Dr. in FY 2023.
- $1,017,500 for preliminary engineering in FY 2023 and $8,528,299 for construction in FY 2025 for a resurfacing project for Crawfordville Road from SR 61 SB to Arden Road.
Project timeline quarters are defined as:
Project Manager
Staff Contact: (850) 219-1060
info@blueprintia.org