Project Description
This project provides multimodal connectivity along the entire corridor from South Adams Street to Apalachee Parkway. It is being constructed in phases and in coordination with utility improvements in the area. Construction began in summer 2021.
Project Improvements
- Roadway reconstruction
- Underground electric
- Enclosed stormwater drainage system
- Multi-use trail
- Landscape buffers between path and roadway
Project Status
- RFQ for CEI services for Phase 2 was advertised in Q2 2023.
- Phase 1 and 4 are complete.
- Design for phase 2 (Pontiac to Diamond) is complete and construction is currently scheduled to begin in Q4 2023.
- Phase 3 (Diamond to Apalachee) is 90% complete and right-of-way acquisition is ongoing.
Project Manager
Junious Brown
Staff Contact: (850) 219-1063